Project planning
Solar Storage Project Checklist: From Site Survey to Commissioning
A field checklist for planning a solar battery storage project, documenting site conditions and verifying installation and commissioning.
Document the site before system selection
Record the location, grid availability and outage pattern, existing generator, roof or ground-mount options, cable routes, equipment room conditions and access for delivery. Build an appliance schedule with operating hours and identify critical circuits. Photos and a simple site sketch can help an installer clarify assumptions.
For community or multi-building projects, map users, operating schedules and who will maintain the equipment. Do not size a shared battery from a single average if important loads run at different times.
Define acceptance checks
Before procurement, agree what documents will be supplied, which tests will be witnessed and how the system will be handed over. Commissioning should be carried out by a qualified installer following manufacturer procedures and applicable requirements; the project owner should receive settings, operating instructions and warranty contacts.
A useful project record captures the installed model numbers, battery configuration, protection settings, monitoring access, commissioning results and any deviations from the approved design.
Report verified results, not assumptions
For a project case study, state the site context, system configuration, measurement period and method. Distinguish measured energy and uptime from estimates, and obtain permission before publishing a customer's name, images or performance data. This produces a credible reference for future solar battery projects without promising identical results at other sites.